Video 135 feet later: Time-lapse video taken of the amazing first Big Lift on June 19.
Leave your comments on Facebook Icon Twitter Icon.

             View Photo Gallery : View Webcams : Quick Facts
Bridge Overview Activity/Progress Press Room Traffic Conditions Community Awareness History Frequently Asked Questions Contact Us
Community Activity
2010 | 2009 | 2008 | 2007 | 2006 | 2005       

Construction Timetable Future In Progress Complete
Phase III - Span by span truss construction
June 2010
Future    
Phase IV - East Bank WBB Approach Substructure
Jan 10
  In Progress  
Phase III - Span 3 - Big Lift
June 2010
    Complete
Phase III - Span 3 - Stick Built Installation
June 2010
  In Progress  
Phase III - Span 2 - Big Lift
November 2010
Future    
Phase IV - Pier IVA Footing
July 2010
    Complete
Phase IV - Pier IV A - Column & Trumpet
August
  In Progress  
Phase IV - Finish WB WBB Deck
Mid August
  In Progress  
Phase IV - Finish WB EBB Deck
November
  In Progress  
Phase IV - Jefferson Highway overpass demolition
October/November
Future    
Phase IV - Pile Driving on the East Bank (Phase I)
October 2010
  In Progress  
 